The project
- New workshop worth M€ 130
- 87,000 m²
- 2-year duration for ASSYSTEM involvement
- Production change in 4 days
- The manufacturer wishes to keep the prime contractor
The solutions
- Scheduling - Feasibility studies
- Assembly & testing coordination
- Operator training coordination
- Process certification
- Cost control
- Project reporting
Results
- Project completed on budget
- Production started on time
- Availability level reached 3 weeks after start of production